22 on filequarterly progress reports filed with RERA
Timeline
RERA registeredJun 2018
Proposed completionFeb 2026
TodaySep 2026
Construction progress
69% overall, as filed
Solid Waste Management And Disposal20%
Water Supply50%
Sewerage50%
Landscaping And Tree Planting50%
Water Conservation Rain Water Harvesting50%
Community Buildings60%
Street Lighting70%
Storm Water Drains80%
Energy Maanagement80%
Internal Roads And Footpaths90%
Boundary Wall90%
Security Service90%
Gym100%
Place Of Worship100%
Swimming Pool100%
Club House100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools1 school within 1km · College or university 1.2km away
HealthcareHospital 640m away
LifestylePark 1.0km away
ShoppingNo supermarket within 2km
Getting around
Expressway 918 mPrimary road 2.0 km · V.I.P. RoadRailway line 1.1 kmRailway station 2.9km away (Telibandha)Limited bus connectivity nearby
Water & environment
Water body 2.4 kmCanal 2.7 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹13.91 Cr declared. What that works out to:
61%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
170 plotted projects still under way within 25 km. Step out ring by ring:
Of the 473 projects the radar draws within 6 km — every kind, every stage — 64 are plotted projects still under way. This list keeps only those, and looks further out.
3 projects within 1 km — showing the nearest 3.
440 m awayResidential Plotted Development
PARK SERENE PHASE-II
ASHIYANA BUILDERS & COLONIZERS · Raipur
2 yr 10 mo
Nov 2024registered
Sep 2027target completion
⚠ no escrow declaredDeclared cost₹13.82 CrAuthorityRERA Chhattisgarh