Complete project overview
MahaRERA · Registration filing- Floors
- 10
- Buildings
- 2
- Parking
- 51 spaces
- Land area
- 948 sq m
- Sanctioned built-up
- 3,002 sq m
Timeline
RERA registeredDec 2023
Proposed completionDec 2026
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Flat fit-out10%
Internal finishes70%
Stairs & lifts75%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
02
Builder’s track record
MahaRERA · Promoter registrationPark View CO-Op Housing Society
SocietyPromoter type
Nashik, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Nashik (M Corp.)
- Taluka
- Nashik
- District
- Nashik
- Pincode
- 422013
- Survey no.
- Plot No 4 and 5 of S.No 692/1/5 and 692/1/6 F.P. No 415
- North boundary
- 50 feet colony road
- East boundary
- Plot No 3 of the same survey number
- South boundary
- remaining part of same survey number
- West boundary
- Pumping station road
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 561m away
HealthcareHospital 213m away · 3 clinics within 1km
LifestyleNo parks within 2km · 15+ restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Mall 472m away · Bank 216m away
Getting around
Expressway 1.7 km · Trimbak RoadPrimary road 73 m · Gangapur RoadNo metro or railway within 5kmLimited bus connectivity nearby
Legal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.