HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
2
Buildings
2
Parking
39 spaces
Land area
2,957 sq m
Sanctioned built-up
4,583 sq m
Recreational open space
505 sq m

Timeline

RERA registeredDec 2022
Proposed completionOct 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Flat fit-out1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Saideep Builders and Developers

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2022–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vada (CT)
Taluka
Vada
District
Palghar
Pincode
421303
Survey no.
Survey No 234/1/A, 235/1/K and 140/7
North boundary
Part of S No234
East boundary
S no 140 and S No 235
South boundary
S No 233
West boundary
Existing Internal road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.9km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 84 mPrimary road 1.7 km · Wada Shahapur RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 393 m · Vaitarna RiverWater body 2.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Wada Nagar Panchayat

Municipal Council
Building Permit
Survey no. Survey No 234/1/A, 235/1/K and 140/7

The promised possession date (31 Oct 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.