HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
988 sq m

Timeline

Construction startAug 2021
RERA registeredSep 2021
Proposed completionAug 2024
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Parth Sarthi BuildersAndDevelopers

IndividualPromoter type
Jaipur, RajasthanBased in
2Projects
1City
2021–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
48 homeson the public record across 2 projects
10,252 sq mbuilt-up filed
2,239 sq mland declared
₹19.06 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Plot no. 113,114,123,124, Shri Dadu Dayal Nagar, E-Block, Gram - Kalyanpura, Jaipur, Sanganer, Jaipur, 302020
Village
Jaipur
Taluka
Sanganer
District
Jaipur
Pincode
302020
What’s nearby
SchoolsNearest school 1.2km away · Library 1.6km away
HealthcareHospital 755m away · 4 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.6km away · Swimming pool within 2km
ShoppingSupermarket 1.6km away
Getting around
Expressway 1.1 km · NH11Primary road 1.5 km · B2 BypassRailway line 1.5 kmRailway station 1.8km awayLimited bus connectivity nearby
Water & environment
Water body 2.2 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹7.35 Cr declared. What that works out to:

18%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 8 Sep 2021 · 4 yrs ago

The promised possession date (13 Aug 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.