HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
30 units
Mix
27 × Existing Member · 2 × 5 BHK · 1 × 3 BHK
Carpet area
103–318 sq mper-unit range, as filed
Floors
18
Buildings
2
Parking
107 spaces
Land area
2,314 sq m

Timeline

RERA registeredJul 2024
Proposed completionJun 2029
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Basement (if any)90%
Plinth90%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

30 units across 13 batches
TypeArea sq mCount
Existing Member1341
Existing Member1033
Existing Member1267
Existing Member1232
5 BHK2581
3 BHK1521
Existing Member1521
Existing Member1597
Existing Member1891
Existing Member1771
5 BHK3181
Existing Member1192
Existing Member1212

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

PEARL QUEEN COOPERATIVE HOUSING SOCIETY LIMITED

SocietyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bandra
Taluka
Andheri
District
Mumbai Suburban
Pincode
400054
Survey no.
51
North boundary
PLOT NO 50
East boundary
TAGORE ROAD
South boundary
NORTH AVENUE
West boundary
PLOT NO 52 53 AND 54
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km · College or university 1.5km away
HealthcareHospital 455m away · 9 clinics within 1km · Pharmacy within 1km
LifestylePark 1.1km away · Playground within 500m · Gym or sports centre 698m away
ShoppingSupermarket 264m away · Convenience store within 1km · Bank 69m away
Getting around
Expressway 1.4 kmPrimary road 435 m · Swami Vivekanand RoadRailway line 809 mRailway station 915m away (Santa Cruz)6 bus stops within 500m
Water & environment
Water body 529 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 51
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.