Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
12
Parking
14 spaces
Land area
3,000 sq m
Sanctioned built-up
4,661 sq m
Recreational open space
301 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Podiums0%
Water conservation…0%
Water Supply50%
Electrical meter r…50%
Storm Water Drains80%
Internal Roads & F…90%
Sewerage (Chamber,…90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Aggregate area of …100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

I G BUILDERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Dahisar
Taluka
Thane
District
Thane
Pincode
400612
Survey no.
SURVEY NO 79 HISSA NO 1B
North boundary
OLD SURVEY NO 351
East boundary
EXISTING 6 METER PROPOSED 12 METER ROAD
South boundary
SURVEY NO 79 HISSA NO 2
West boundary
SURVEY NO 79 HISSA NO 1A
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 kmPrimary road 4.4 km · Kalyan - Shil RoadRailway line 294 mRailway station 4.0km away (Nilaje)Limited bus connectivity nearby
Water & environment
River 1.4 kmWater body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mumbai Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. SURVEY NO 79 HISSA NO 1B

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mumbai Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 152 RERA projects0.8% of Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
93
On record
7,406 flats · 157 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 0 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.