Complete project overview

UP-RERA · Registration filing
Units
576 units
Unit mix
576 × 1 BHK
Carpet area
12–23 sq mper unit, as filed
Floors
4
Blocks
12
Land area
23,539 sq m

Timeline

Project startedNov 2019
RERA registeredMar 2020
Proposed completionAug 2020
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

576 units across 48 batches
BuildingFloorTypeArea sq mCount
Block No 111 BHK2312
Block No 121 BHK2312
Block No 131 BHK2312
Block No 141 BHK2312
Block No 1011 BHK2312
Block No 1021 BHK2312
Block No 1031 BHK2312
Block No 1041 BHK2312
Block No 1111 BHK2312
Block No 1121 BHK2312
Block No 1131 BHK2312
Block No 1141 BHK2312
Block No 1211 BHK2312
Block No 1221 BHK2312
Block No 1231 BHK2312
Block No 1241 BHK2312
Block No 211 BHK2312
Block No 221 BHK2312
Block No 231 BHK2312
Block No 241 BHK2312
Block No 311 BHK2312
Block No 321 BHK2312
Block No 331 BHK2312
Block No 341 BHK2312
Block No 411 BHK1212
Block No 421 BHK2312
Block No 431 BHK2312
Block No 441 BHK2312
Block No 511 BHK2312
Block No 521 BHK2312
Block No 531 BHK2312
Block No 541 BHK2312
Block No 611 BHK2312
Block No 621 BHK2312
Block No 631 BHK2312
Block No 641 BHK2312
Block No 711 BHK2312
Block No 721 BHK2312
Block No 731 BHK2312
Block No 741 BHK2312
Block No 811 BHK2312
Block No 821 BHK2312
Block No 831 BHK2312
Block No 841 BHK2312
Block No 911 BHK2312
Block No 921 BHK2312
Block No 931 BHK2312
Block No 941 BHK2312

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

MEERUT DEVELOPMENT AUTHORITY

Competent authorityPromoter type
10Registered projects
8Projects
1City
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,944 homes · 217 plotson the public record across 8 projects
57,612 sq mplotted area
1,93,218 sq mland declared
₹4519377.64 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Meerut
Tehsil
Meerut
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 979 mPrimary road 2.8 km · Garh RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 461 m · Kali NadiCanal 523 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹22.57 Cr declared to build 576 flats. What that works out to:

₹3.92 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 1 Jan 1900 · 126 yrs ago
Building Permit no. 1564/PMAY/SECEMDAMRT

The promised possession date (30 Aug 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1564/PMAY/SECEMDAMRT on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.