Complete project overview

K-RERA · Registration filing
Units
45 units
Mix
23 × Studio · 9 × 1BHK · 8 × 2BHK · 5 × 3BHK
Booked
13 of 45 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,503 sq m
Floor area
3,155 sq m
Description
Prayag

Timeline

Project startedMar 2021
RERA registeredDec 2021
Proposed completionJun 2023
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

32 of 45 available
TypeArea sq mAvailable
1BHK385 of 8
1BHK491 of 1
2BHK771 of 2
2BHK492 of 4
2BHK751 of 1
2BHK551 of 1
3BHK934 of 4
3BHK801 of 1
Studio341 of 1
Studio311 of 3
Studio274 of 7
Studio224 of 5
Studio241 of 2
Studio202 of 2
Studio213 of 3

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SREEPATHI ASSOCIATES BUILDERS & PROMOTERS

PartnershipPromoter type
Thrissur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
3Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
67 homeson the public record across 3 projects
5,398 sq mbuilt-up filed
2,657 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Guruvayoor MunicipalityMunicipality2 of 3 projects
Guruvayoor Municipal CouncilLocal body (LSGI)this project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Parath Lane
Village
GURUVAYUR
Taluk
Chavakkad
District
Thrissur
Pincode
680101
Survey no.
85/7A
Patta no.
12979, 12564
What’s nearby
Schools1 school within 500m · 10 educational institutions within 1km · College or university 871m away
HealthcareHospital 343m away · Pharmacy within 500m
LifestylePark 1.8km away · Gym or sports centre 1.8km away · 34+ restaurants and cafes within 1km
ShoppingSupermarket 255m away · Mall 1.0km away · Convenience store within 1km
Getting around
Expressway 2.4 kmPrimary road 94 m · Guruvayoor - Althara - Ponnani RoadRailway line 805 mRailway station 1.1km away (Guruvayur)2 bus stops within 500m
Water & environment
Canal 75 m · guruvayoor valiya thoduWater body 108 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Guruvayoor Municipal Council

Local body (LSGI)
approved 27 Jul 2022 · 4 yrs ago
Building Permit no. BA/188/19-20Survey no. 85/7A

The promised possession date (30 Jun 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BA/188/19-20 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.