Complete project overview

MahaRERA · Registration filing
Floors
11
Buildings
2
Land area
2,940 sq m
Sanctioned built-up
1,813 sq m
Recreational open space
289 sq m

Timeline

RERA registeredJul 2020
Proposed completionSep 2023
TodayJul 2026
Construction progress
Podiums0%
Water Supply0%
Energy managemcnt0%
Aggregate area of …0%
Electrical meter r…50%
External finishes90%
OC-readiness95%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
Internal Roads & F…100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHAKTI DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
21Projects
12Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,639 homeson the public record across 21 projects
65,623 sq mbuilt-up filed
86,290 sq mland declared
₹163.24 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Others4 of 15 projects
Ahmedabad Urban Development AuthorityUrban Development Authority3 of 15 projects
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 15 projects
Mumbai Metropolitan Region Development AuthorityMetropolitan Development Authoritythis project1 of 15 projects
Nadiad MunicipalityMunicipal / Corporation1 of 15 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 15 projects
Surat Municipal CorporationMunicipal / Corporation1 of 15 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 15 projects
Vasai Virar City Municipal CorporationMunicipal Corporation1 of 15 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
kon (CT)
Taluka
Bhiwandi
District
Thane
Pincode
421302
Survey no.
SURVEY NUMBER 15 HISSA 4A 4B
North boundary
SURVEY NUMBER 15 HISSA 3
East boundary
SURVEY NO 16
South boundary
SURVEY NUMBER 15 HISSA 6-8
West boundary
SURVEY NO 10
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 369m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 285m away
Getting around
Expressway 12 m · Agra RoadPrimary road 943 mRailway line 1.4 kmRailway station 1.4km away (Bhivandi Road)2 bus stops within 500m
Water & environment
Water body 1.0 kmRiver 2.3 km · Kamvadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mumbai Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. SURVEY NUMBER 15 HISSA 4A 4B

The promised possession date (2 Sep 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mumbai Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 152 RERA projects0.8% of Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
93
On record
7,406 flats · 157 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.