HORIZON
Share

Pristine KYRA

P52100055515 · MahaRERA · https://gethorizon.in/projects/pristine-kyra-lohgaon-haveli-e8xpqudw

01

Complete project overview

MahaRERA · Registration filing
Project name
Pristine KYRA
Units
292 units
Floors
14
Buildings
12
Parking
560 spaces
Land area
13,612 sq m
Sanctioned built-up
54,751 sq m
Recreational open space
1,322 sq m

Timeline

RERA registeredApr 2024
Proposed completionMar 2029
TodaySep 2026
Construction progress
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Stilt floor30%
Internal finishes40%
Superstructure93%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Highspot Realtors LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
361 homeson the public record across 2 projects
60,476 sq mbuilt-up filed
17,110 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Pune Municipal Corporation, PuneMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Highspot Realtors LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
LOHGAON
Taluka
Haveli
District
Pune
Pincode
411014
Survey no.
S No 230A/2 Lohgaon
North boundary
S No 230A-1
East boundary
S No 210 and 229
South boundary
S No 230A-3 and 20M wide road
West boundary
S No 230A-2-1
What’s nearby
Schools2 schools within 500m · 6 educational institutions within 1km · College or university 501m away
HealthcareHospital 1.7km away · 1 clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 459m away · Swimming pool within 2km
ShoppingNo supermarket within 2km · Bank 643m away
Getting around
Expressway 3.5 kmPrimary road 144 m · Lohgaon - Wagholi RoadRailway station 4.0km away (Ramwadi Station)2 bus stops within 500mAirport 1.4km away
Water & environment
Water body 1.6 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹70,954per sq yd
₹84,860per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “LOHGAON”.
In force
2026-2027 schedule
Spread
₹40,218₹85,344 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S No 230A/2 Lohgaon
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,200 residential projects still under way within 25 km. Step out ring by ring:

37 projects within 1 km — showing the nearest 6.

LOHGAONResidential / Group Housing

ARUNITA TOWERS

ARUNITA RESIDENCY LLP

Nov 2023registered
Dec 2028target completion
Government Guidance Rate₹70,954/sq ydScale64 flatsAuthorityMahaRERA
LahagaonResidential / Group Housing

NAMAY RESIDENCY

MANGAL PROPERTIES

Mar 2025registered
Dec 2027target completion
Government Guidance Rate₹70,954/sq ydScale20 flatsAuthorityMahaRERA
LOHGAONResidential / Group Housing

Viman Avenue

Prem Constructions

Jul 2025registered
Mar 2028target completion
Government Guidance Rate₹70,954/sq ydScale16 flatsAuthorityMahaRERA
LahagaonResidential / Group Housing

Belmont Skyverse

Belmont Realty

Apr 2024registered
Aug 2028target completion
Government Guidance Rate₹70,954/sq ydScale141 flatsAuthorityMahaRERA
LahagaonMixed

108 Elevate

M K INFRA

Mar 2026registered
Dec 2030target completion
Government Guidance Rate₹70,954/sq ydScale110 flatsAuthorityMahaRERA
LOHGAONMixed

Audumber Plaza

Akruti Construction

Oct 2025registered
Dec 2028target completion
Government Guidance Rate₹70,954/sq ydScale7 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.