HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Buildings
2
Parking
62 spaces
Land area
1,036 sq m
Sanctioned built-up
2,586 sq m

Timeline

RERA registeredJan 2020
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
OC-readiness30%
Electrical meter r…50%
External finishes67%
Water Supply70%
Fire protection an…70%
Stilt floor75%
Flat fit-out75%
Sewerage (Chamber,…80%
Internal finishes82%
Stairs & lifts83%
Excavation100%
Podiums100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

JV REALITIES

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2020–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400601
Survey no.
16/B
North boundary
ADJ CTS NO 16A AND 17
East boundary
ADJ 4-50 MW PROP ROAD
South boundary
ADJ 9-00 MW DP ROAD CTS NO 15 AND 16C
West boundary
CTS NO 6
What’s nearby
SchoolsNearest school 1.1km away · 3 educational institutions within 1km · College or university 618m away
HealthcareHospital 231m away · 10 clinics within 1km · Pharmacy within 500m
LifestylePark 735m away · Gym or sports centre 1.7km away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Mall 1.7km away · Bank 178m away
Getting around
Expressway 1.5 kmPrimary road 431 m · Jail RoadRailway line 802 mRailway station 991m away (Thane)15 bus stops within 500m
Water & environment
Water body 568 m · Jail LakeRiver 771 m · Thane Creek
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 16/B
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.