Complete project overview

RERA Karnataka · Registration filing
Status
New Project Launch
Towers
1
Land area
1,762 sq m
FAR sanctioned
15216.6
Covered area
893 sq m
Open area
869 sq m

Timeline

Project startedOct 2020
RERA registeredJun 2022
Proposed completionDec 2027
TodayJul 2026
Construction progress

80% overall, as filed

Amenities40%
Internal infra69%
Finishing73%
External infra79%
Super-structure84%
Common areas95%
Sub-structure100%
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Karnataka · Promoter registration

Puravankara Limited

Bengaluru UrbanBased in
38Projects
8Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,562 homes · 449 plotson the public record across 38 projects
3,06,443 sq mbuilt-up filed
98,510 sq mplotted area
5,68,546 sq mland declared
₹6571.59 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation10 of 37 projects
BDA - Bangalore Development AuthorityUrban Development Authority8 of 37 projects
Local Planning AuthorityTown & Country Planning (DTCP)this project5 of 37 projects
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)4 of 37 projects
BIAPPA - Bangalore Airport Area Planning AuthorityUrban Development Authority3 of 37 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation3 of 37 projects
P 2373/2019/(395 And Other)/M/E Ward/Deonar E/Cc/1/New1 of 37 projects
Pmc1 of 37 projects
Thane Municipal CorporationMunicipal Corporation1 of 37 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 37 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru South
District
Bengaluru Urban
Pincode
000000
Address
Survey No 19 Mallasandra Village, Kanakapura Road
What’s nearby
Schools1 school within 1km
HealthcareNearest hospital 2.6km away · 3 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 484m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 649m away · Convenience store within 500m · ATM within 500m
Getting around
Expressway 1.5 km · Kanakapura RoadPrimary road 5.0 km · Bannerghatta RoadMetro station 1.6km away (Silk Institute)Bus stop within 500m
Water & environment
Water body 357 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹86.39 Cr declared. What that works out to:

28%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Local Planning Authority

Town & Country Planning (DTCP)
Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Local Planning Authority

Town & Country Planning

Has approved 1,518 RERA projectsabout 1 in 6 in Karnataka.

a mixed market42% apartments · 58% plotted layouts.

Builders
1,212
On record
42,750 flats · 54,584 plots
Reach
128 taluks
Since
2017

More layout-heavy than Karnataka overall — 58% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.