01
Complete project overview
MahaRERA · Registration filing- Floors
- 8
- Parking
- 42 spaces
- Land area
- 880 sq m
- Sanctioned built-up
- 2,253 sq m
Timeline
RERA registeredJun 2024
Proposed completionMay 2027
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Superstructure15%
Basement (if any)85%
Plinth85%
Excavation100%
02
Builder’s track record
MahaRERA · Promoter registrationNANDKUSUM INFRA LLP
PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- DOMBIVLI
- Taluka
- Kalyan
- District
- Thane
- Pincode
- 421202
- Survey no.
- SURVEY NO 35 NEW SURVEY NO 129 OLD HISSA NO 1 & 12
- North boundary
- SURVEY NO 36 HISSA NO 6
- East boundary
- SURVEY NO 36 HISSA NO 6
- South boundary
- 150 SQ FT RING ROAD
- West boundary
- SURVEY NO 37 HISSA NO 1 B
What’s nearby
SchoolsNearest school 1.0km away
HealthcareHospital 430m away · 1 clinic within 1km
LifestylePark 837m away · Gym or sports centre 1.7km away
ShoppingSupermarket 1.1km away
Getting around
Expressway 4.5 km · Mumbai Agra National HighwayPrimary road 3.2 km · Kalyan - Shil RoadRailway line 362 mRailway station 467m away (Kopar)Limited bus connectivity nearby
Water & environment
River 962 mWater body 1.2 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.