Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
27 spaces
Land area
457 sq m
Sanctioned built-up
1,067 sq m

Timeline

RERA registeredAug 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Street Lighting0%
Flat fit-out85%
Stairs & lifts85%
OC-readiness90%
External finishes92%
Internal finishes95%
Water Supply95%
Sewerage (Chamber,…95%
Water conservation…95%
Electrical meter r…95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

HANSRAJ DATTOBA JADHAV

IndividualPromoter type
Latur, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Latur (M Cl)
Taluka
Latur
District
Latur
Pincode
413512
Survey no.
PLOT NO 2,7 SY.NO.25/D, AT KANHERI, AUSA RAOD LATUR
North boundary
6 METER WIDE ROAD
East boundary
PLOT NO 6 AND 3
South boundary
12 MEER WIDE ROAD
West boundary
PLOT NO 8 AND 1
What’s nearby
SchoolsNearest school 1.6km away · 4 educational institutions within 1km · College or university 630m away
HealthcareHospital 433m away · 1 clinic within 1km
LifestylePark 968m away · Gym or sports centre 993m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 134m away · Mall 1.1km away · Bank 574m away
Getting around
Expressway 179 mPrimary road 329 m · Ring RoadNo metro or railway within 5km2 bus stops within 500m
Water & environment
Canal 1.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation Latur

Municipal Corporation
Building Permit
Survey no. PLOT NO 2,7 SY.NO.25/D, AT KANHERI, AUSA RAOD LATUR
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.