HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
26
Buildings
2
Parking
65 spaces
Land area
1,107 sq m
Sanctioned built-up
5,271 sq m
Recreational open space
141 sq m

Timeline

RERA registeredApr 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Podiums10%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Shree Shankheshwar Enterprises

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
3Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
83 homeson the public record across 3 projects
10,513 sq mbuilt-up filed
3,951 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 2 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
District
Mumbai City
Pincode
400014
Survey no.
26/26 ,27/26
North boundary
CTS No - 30-26 and 31-26
East boundary
CTS No - 28-26
South boundary
15M Wide Govindji Keni Road
West boundary
CTS No - 11-26
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 1.1km away
HealthcareHospital 432m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 1.3km away · Gym or sports centre 560m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Mall 1.5km away · Bank 442m away
Getting around
Expressway 69 mPrimary road 732 m · Senapati Bapat MargRailway line 462 m · Central Railway (Slow)Railway station 529m away (Parel)6 bus stops within 500m
Water & environment
Water body 669 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 26/26 ,27/26
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.