HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
5 spaces
Land area
568 sq m
Sanctioned built-up
907 sq m

Timeline

RERA registeredJun 2025
Proposed completionDec 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Flat fit-out30%
Stairs & lifts30%
External finishes30%
Internal finishes50%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RIDDHI SIDDHI APARTMENT

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kardal
Taluka
Palghar
District
Palghar
Pincode
401102
Survey no.
GUT NO 57/3 PLOT NO 17
North boundary
PLOT NO 18
East boundary
FOREST LAND
South boundary
PLOT NO 16
West boundary
PLOT NO 9 AND 10
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 706m away
LifestylePark 2.0km away
ShoppingNo supermarket within 2km
Getting around
Primary road 644 mRailway line 383 mRailway station 976m away (Saphale)Limited bus connectivity nearby
Water & environment
Water body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Jilhadhikari Karyalaya Palghar

Building Permit
Survey no. GUT NO 57/3 PLOT NO 17
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.