HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
48
Buildings
2
Parking
218 spaces
Land area
810 sq m
Sanctioned built-up
19,978 sq m

Timeline

RERA registeredNov 2023
Proposed completionOct 2029
TodayJul 2026
Construction progress
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Stairs & lifts8%
Internal finishes41%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

CCI PROJECTS PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
8Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
904 homeson the public record across 8 projects
2,02,013 sq mbuilt-up filed
3,17,812 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Magathane
Taluka
Borivali
District
Mumbai Suburban
Pincode
400066
Survey no.
163-A & 165
North boundary
CTS 165 part of Village Magathane
East boundary
CTS 165 part of Village Magathane
South boundary
CTS 165 part of Village Magathane
West boundary
CTS 165 part of Village Magathane
What’s nearby
Schools1 school within 1km · Library 1.9km away
HealthcareHospital 379m away · 2 clinics within 1km
LifestylePark 712m away · Gym or sports centre 615m away · Swimming pool within 2km
ShoppingSupermarket 874m away · Mall 690m away · Convenience store within 500m
Getting around
Expressway 255 m · Western Express HighwayPrimary road 1.1 kmRailway line 169 m · FCIMetro station 269m away (Magathane)Bus stop within 1km
Water & environment
River 1.3 km · Dahisar RiverWater body 1.9 km · Veer Savarkar Udyan Pond
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 163-A & 165
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.