Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
24 spaces
Land area
1,000 sq m
Sanctioned built-up
1,485 sq m

Timeline

RERA registeredAug 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Water conservation…100%
External finishes1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAIRA BUILDERS AND DEVELOPERS

PartnershipPromoter type
Sindhudurg, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Banda (CT)
Taluka
Sawantwadi
District
Sindhudurg
Pincode
416511
Survey no.
SURVEY NO 151A/28
North boundary
SHIKHA FAMILY PROPERTY
East boundary
VIJAY SHAMBHEKAR PROPERTY
South boundary
NH 66
West boundary
VISHAL CHINESE CORNER
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 96 m · Mumbai - Goa HighwayPrimary road 100 mNo metro or railway within 5kmBus stop within 500m
Water & environment
Canal 550 mRiver 1.0 km · Terekhol
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Grampanchayat Banda

Gram Panchayat
Building Permit
Survey no. SURVEY NO 151A/28
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Legal & regulatory record
Litigation1 case on record, earliest 2022
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.