ROYAL CREST

Timeline

Project startedJan 2025
RERA registeredMar 2025
Proposed completionAug 2029
TodayJul 2026
Construction progress

5% overall, as filed

Basement(s) and Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation80%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

70 of 70 available
TypeArea sq mAvailable
3BHK2,91028 of 28
2BHK3,42242 of 42

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

PALAZHI HOMES PRIVATE LIMITED

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
1Projects
1Cities
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
KATTELA
Village
CHERUVAKKAL
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695017
Survey no.
86/3
Patta no.
26360
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away · Library 1.8km away
HealthcareHospital 1.0km away · Clinic within 2km
LifestylePark 1.2km away · Gym or sports centre 2.0km away
ShoppingSupermarket 1.0km away · Convenience store within 1km · Bank 955m away
Getting around
Expressway 1.0 km · Salem - Kochi - Kanyakumari RoadPrimary road 2.5 kmRailway line 1.5 kmRailway station 1.8km away (Veli)Bus stop within 1km
Water & environment
Water body 152 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 7 Sep 2024 · 1 yr ago
Building Permit no. UE2/BA/113/24Survey no. 86/3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE2/BA/113/24 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.