01
Complete project overview
MahaRERA · Registration filing- Floors
- 7
- Buildings
- 2
- Parking
- 52 spaces
- Land area
- 2,064 sq m
- Sanctioned built-up
- 2,423 sq m
Timeline
RERA registeredMay 2026
Proposed completionDec 2027
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Fire protection an…0%
Open Parking0%
Excavation100%
Plinth100%
02
Builder’s track record
MahaRERA · Promoter registrationShubhankar Developers
PartnershipPromoter type
Solapur, MAHARASHTRABased in
5Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
102 homeson the public record across 5 projects
16,494 sq mbuilt-up filed
18,466 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Barshi (M Cl)
- Taluka
- Barshi
- District
- Solapur
- Pincode
- 413411
- Survey no.
- plot_no - city_survey_gut_no 1543/2/3 final_plot_no - sector_no - mauje BARSHI road_street MANGIRE MALA society -
- North boundary
- Road
- East boundary
- Road
- South boundary
- Plot
- West boundary
- Plot
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 217m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.4 km · Barshi BypassPrimary road 498 mRailway line 2.2 kmRailway station 2.8km away (Barsi Town)Limited bus connectivity nearby
Water & environment
Water body 479 mCanal 2.5 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.