HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
29 spaces
Land area
330 sq m
Sanctioned built-up
805 sq m

Timeline

RERA registeredFeb 2024
Proposed completionOct 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Community Building…0%
Treatment And Disp…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Internal finishes60%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Prakash Maruti Gharat

IndividualPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2024–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vadghar (CT)
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Plot No 161, Sector R-4, Pushpak Node Karanjade, Tal Panvel, Dist Raigad 410206
North boundary
Plot No 158
East boundary
Plot No 159
South boundary
9 Meter Wide Road
West boundary
Plot No 162
What’s nearby
SchoolsNearest school 1.6km away
HealthcareHospital 888m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 700 m · Uran RoadPrimary road 182 m · Uran RoadRailway line 788 m · JNPTRailway station 2.5km away (Khandeshwar)Limited bus connectivity nearby
Water & environment
Canal 240 mRiver 449 m · Kalundre RiverWater body 471 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. Plot No 161, Sector R-4, Pushpak Node Karanjade, Tal Panvel, Dist Raigad 410206

The promised possession date (31 Oct 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.