01
Complete project overview
MahaRERA · Registration filing- Floors
- 23
- Buildings
- 2
- Parking
- 416 spaces
- Land area
- 1,47,596 sq m
- Sanctioned built-up
- 9,283 sq m
- Recreational open space
- 709 sq m
Timeline
RERA registeredApr 2023
Proposed completionJun 2028
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water conservation…0%
Internal finishes6%
Basement (if any)80%
Stilt floor80%
Superstructure81%
Excavation100%
Plinth100%
02
Builder’s track record
MahaRERA · Promoter registrationEvie Real Estate Private Limited
CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
11Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,313 homeson the public record across 11 projects
1,84,171 sq mbuilt-up filed
7,41,921 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Kanjurmarg
- Taluka
- Kurla
- District
- Mumbai Suburban
- Pincode
- 400042
- Survey no.
- 1004 ,1005 ,1005/1, 1006,1007(pt), 1007/3(pt), 1007/4, 1009(pt),1009/5 &6, 1010(pt), 1013(pt), 1014(pt), 1014/1 to 6, 1017, 1017/1 to 6, 1018, 1018/1 to 9
- North boundary
- ROS 1 point 5 reservation
- East boundary
- 12 mtr wide layout road
- South boundary
- 12 mtr layout road
- West boundary
- AOS Podium Floors
What’s nearby
Schools4 schools within 1km · 4 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 368m away · 1 clinic within 1km
LifestylePark 1.6km away
ShoppingSupermarket 670m away · Mall 1.1km away
Getting around
Expressway 745 mPrimary road 483 m · Jogeshwari-Vikroli Link RoadRailway line 435 m · Central Railways Express LineRailway station 529m away (Kanjur Marg)Bus stop within 1km
Water & environment
Water body 1.8 km
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
3 complaints on MahaRERA’s register for this project — 3 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.