RERA Telangana · Registration filing
Units
15 units
Unit mix
15 × 2BHK
Saleable area
115–134 sq mper unit, as filed
Floors
5
Land area
697 sq m
Built-up area
2,100 sq m
Road widening
56 sq mland set aside for road widening

Timeline

RERA approvedSep 2022
Proposed completionSep 2025
TodayJul 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 15 available
BuildingFloorTypeArea sq mAvailable
S PRIDE12BHK1342 of 2
S PRIDE12BHK1151 of 1
S PRIDE22BHKmortgaged1341 of 1
S PRIDE22BHKmortgaged1151 of 1
S PRIDE22BHK1341 of 1
S PRIDE32BHK1342 of 2
S PRIDE32BHK1151 of 1
S PRIDE42BHK1341 of 1
S PRIDE42BHK1151 of 1
S PRIDE42BHK1331 of 1
S PRIDE52BHK1332 of 2
S PRIDE52BHK1151 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

FORTUNE DEVELOPERS

PartnershipPromoter type
Khammam, TelanganaBased in
24Projects
11Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
758 homeson the public record across 24 projects
61,188 sq mbuilt-up filed
36,650 sq mland declared
₹132.53 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
A Design Studio2 of 15 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 15 projects
Commissioner, ULBMunicipal / Corporation1 of 15 projects
Director, Town and Country PlanningTown & Country Planning (DTCP)1 of 15 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project1 of 15 projects
Manoj Tatooskar1 of 15 projects
Nagpur Municipal CorporationMunicipal Corporation1 of 15 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 15 projects
Pune Minicipal Corporation1 of 15 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 15 projects
Sangamner Municipal CouncilMunicipal Council1 of 15 projects
Siddharth Harishchandrakar1 of 15 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 15 projects
Vikas Dhere1 of 15 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
PAKABANDA
Mandal
Khammam (Urban) Mandal
District
Khammam
Pincode
507002
North boundary
PLOT NO 57 58 59
East boundary
12 19 MT WIDE EXISTING 18 28 MT WIDE PROPOSED ROAD
South boundary
12 19 MT WIDE EXIST ROAD
West boundary
PLOT NO 47
What’s nearby
Schools3 schools within 500m · 16 educational institutions within 1km · College or university 637m away
HealthcareHospital 230m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 1.5km away · Gym or sports centre 727m away · 27+ restaurants and cafes within 1km
ShoppingSupermarket 460m away · Mall 304m away · Convenience store within 500m
Getting around
Expressway 2.2 km · Khammam BypassPrimary road 817 mRailway line 83 mRailway station 486m away (Khammam)Bus stop within 1km
Water & environment
Water body 704 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit
Survey no. 105/1 & 42/2

The promised possession date (24 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.