Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
58 spaces
Land area
2,138 sq m
Sanctioned built-up
6,519 sq m

Timeline

RERA registeredOct 2024
Proposed completionMar 2028
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Energy managemcnt0%
Fire protection an…0%
Open Parking0%
Internal finishes20%
Superstructure60%
Excavation100%
Basement (if any)100%
Stilt floor100%
Water Supply100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

FORTUNE DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
24Projects
11Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
758 homeson the public record across 24 projects
61,188 sq mbuilt-up filed
36,650 sq mland declared
₹132.53 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
A Design Studio2 of 15 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 15 projects
Commissioner, ULBMunicipal / Corporation1 of 15 projects
Director, Town and Country PlanningTown & Country Planning (DTCP)1 of 15 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 15 projects
Manoj Tatooskar1 of 15 projects
Nagpur Municipal CorporationMunicipal Corporation1 of 15 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 15 projects
Pune Minicipal Corporationthis project1 of 15 projects
Rajkot Municipal CorporationMunicipal / Corporation1 of 15 projects
Sangamner Municipal CouncilMunicipal Council1 of 15 projects
Siddharth Harishchandrakar1 of 15 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 15 projects
Vikas Dhere1 of 15 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pune (M Corp.)
Taluka
Pune City
District
Pune
Pincode
411004
Survey no.
FIANL PLOT NO 590/B (I.E.590/1+590/2) C.T.S NO 1241
North boundary
BY FINAL PLOT NO 589
East boundary
BY FINAL PLOT NO 591
South boundary
BY INTERNAL ROAD
West boundary
BY APTE ROAD
What’s nearby
Schools5 schools within 500m · 14 educational institutions within 1km · College or university 715m away
HealthcareHospital 148m away · 29 clinics within 1km · Pharmacy within 1km
Lifestyle1 park within 500m · Gym or sports centre 677m away · 81+ restaurants and cafes within 1km
ShoppingSupermarket 1.6km away · Convenience store within 1km · Bank 265m away
Getting around
Expressway 1.0 km · Shivaji RoadPrimary road 231 m · Jangli Maharaj PathRailway line 1.4 km · Mumbai–Pune RailwayMetro station 384m away (Chhatrapati Sambhaji Udyan)Bus stop within 1km
Water & environment
River 401 m · MuthaWater body 438 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Minicipal Corporation

Building Permit
Survey no. FIANL PLOT NO 590/B (I.E.590/1+590/2) C.T.S NO 1241
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.