HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
25 units
Unit mix
25 × 2BHK
Saleable area
97–112 sq mper unit, as filed
Floors
5
Land area
1,000 sq m
Built-up area
2,932 sq m

Timeline

RERA approvedMar 2018
Proposed completionMay 2021
TodayJul 2026
Construction progress

31.5% overall, as filed

Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure15%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

25 of 25 available
BuildingFloorTypeArea sq mAvailable
112BHK1121 of 1
112BHK971 of 1
112BHK1081 of 1
112BHK1042 of 2
122BHKmortgaged1121 of 1
122BHKmortgaged971 of 1
122BHK1042 of 2
122BHKmortgaged1081 of 1
132BHK1121 of 1
132BHK971 of 1
132BHK1081 of 1
132BHK1042 of 2
142BHK1121 of 1
142BHK971 of 1
142BHK1081 of 1
142BHK1042 of 2
152BHK1121 of 1
152BHK971 of 1
152BHK1081 of 1
152BHK1042 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

S. V. SAI BUILDERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
7Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
435 homeson the public record across 7 projects
48,429 sq mbuilt-up filed
28,623 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
Adithya Nagar
Village
Adibatla
Mandal
Ibrahimpatnam
District
Ranga Reddy
Pincode
501510
North boundary
33 feet wide road
East boundary
Plot Nos 134 and 137
South boundary
33 feet wide road
West boundary
Plot Nos 130 and 141
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.7km away
LifestylePark 666m away
ShoppingNo supermarket within 2km
Getting around
Primary road 4.1 km · Hyderabad - Nagarjuna Sagar RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.7 km
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Wet Land double crop, Dry land. The state classes land per survey— confirm your plot’s survey number is House Sites.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹375/sq ydHouse Sites

₹448/sq m · effective Jan 2013

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 69

The promised possession date (21 May 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.