01

Complete project overview

RERA Telangana · Registration filing
Units
90 units
Unit mix
75 × 2BHK, 15 × 3BHK
Saleable area
79–135 sq mper unit, as filed
Floors
5
Land area
3,641 sq m
Built-up area
11,135 sq m

Timeline

RERA approvedApr 2017
Proposed completionDec 2020
TodayJul 2026
Construction progress

21.5% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal finishes15%
Excavation100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

37 of 90 available
BuildingFloorTypeArea sq mAvailable
S V SHANTINIKETAN13BHK1301 of 1
S V SHANTINIKETAN13BHK1180 of 1
S V SHANTINIKETAN12BHK960 of 1
S V SHANTINIKETAN12BHK820 of 1
S V SHANTINIKETAN12BHK990 of 1
S V SHANTINIKETAN12BHK970 of 1
S V SHANTINIKETAN12BHK790 of 1
S V SHANTINIKETAN13BHK1351 of 1
S V SHANTINIKETAN12BHK800 of 1
S V SHANTINIKETAN12BHK1010 of 1
S V SHANTINIKETAN12BHK1010 of 1
S V SHANTINIKETAN12BHK1110 of 1
S V SHANTINIKETAN12BHK1090 of 2
S V SHANTINIKETAN12BHK1110 of 1
S V SHANTINIKETAN12BHK1020 of 1
S V SHANTINIKETAN12BHK1100 of 1
S V SHANTINIKETAN12BHK1091 of 1
S V SHANTINIKETAN22BHKmortgaged961 of 1
S V SHANTINIKETAN22BHKmortgaged821 of 1
S V SHANTINIKETAN22BHKmortgaged991 of 1
S V SHANTINIKETAN22BHKmortgaged970 of 1
S V SHANTINIKETAN22BHKmortgaged791 of 1
S V SHANTINIKETAN23BHKmortgaged1351 of 1
S V SHANTINIKETAN22BHK800 of 1
S V SHANTINIKETAN22BHKmortgaged1011 of 1
S V SHANTINIKETAN22BHK1010 of 1
S V SHANTINIKETAN22BHKmortgaged1111 of 1
S V SHANTINIKETAN22BHK1090 of 2
S V SHANTINIKETAN22BHKmortgaged1111 of 1
S V SHANTINIKETAN22BHK1020 of 1
S V SHANTINIKETAN22BHKmortgaged1101 of 1
S V SHANTINIKETAN22BHKmortgaged1091 of 1
S V SHANTINIKETAN23BHK1181 of 1
S V SHANTINIKETAN23BHK1301 of 1
S V SHANTINIKETAN32BHK961 of 1
S V SHANTINIKETAN32BHK821 of 1
S V SHANTINIKETAN32BHK990 of 1
S V SHANTINIKETAN32BHK970 of 1
S V SHANTINIKETAN32BHK790 of 1
S V SHANTINIKETAN33BHK1350 of 1
S V SHANTINIKETAN32BHK800 of 1
S V SHANTINIKETAN32BHK1010 of 1
S V SHANTINIKETAN32BHK1010 of 1
S V SHANTINIKETAN32BHK1110 of 1
S V SHANTINIKETAN32BHK1090 of 2
S V SHANTINIKETAN32BHK1110 of 1
S V SHANTINIKETAN32BHK1020 of 1
S V SHANTINIKETAN32BHK1100 of 1
S V SHANTINIKETAN32BHK1091 of 1
S V SHANTINIKETAN33BHK1181 of 1
S V SHANTINIKETAN33BHK1301 of 1
S V SHANTINIKETAN42BHK960 of 1
S V SHANTINIKETAN42BHK821 of 1
S V SHANTINIKETAN42BHK990 of 1
S V SHANTINIKETAN42BHK970 of 1
S V SHANTINIKETAN42BHK790 of 1
S V SHANTINIKETAN43BHK1350 of 1
S V SHANTINIKETAN42BHK800 of 1
S V SHANTINIKETAN42BHK1010 of 1
S V SHANTINIKETAN42BHK1010 of 1
S V SHANTINIKETAN42BHK1110 of 1
S V SHANTINIKETAN42BHK1091 of 2
S V SHANTINIKETAN42BHK1111 of 1
S V SHANTINIKETAN42BHK1021 of 1
S V SHANTINIKETAN42BHK1100 of 1
S V SHANTINIKETAN42BHK1091 of 1
S V SHANTINIKETAN43BHK1180 of 1
S V SHANTINIKETAN43BHK1300 of 1
S V SHANTINIKETAN52BHK961 of 1
S V SHANTINIKETAN52BHK820 of 1
S V SHANTINIKETAN52BHK991 of 1
S V SHANTINIKETAN52BHK970 of 1
S V SHANTINIKETAN52BHK790 of 1
S V SHANTINIKETAN53BHK1351 of 1
S V SHANTINIKETAN52BHK801 of 1
S V SHANTINIKETAN52BHK1011 of 1
S V SHANTINIKETAN52BHK1010 of 1
S V SHANTINIKETAN52BHK1111 of 1
S V SHANTINIKETAN52BHK1092 of 2
S V SHANTINIKETAN52BHK1111 of 1
S V SHANTINIKETAN52BHK1021 of 1
S V SHANTINIKETAN52BHK1100 of 1
S V SHANTINIKETAN52BHK1091 of 1
S V SHANTINIKETAN53BHK1181 of 1
S V SHANTINIKETAN53BHK1300 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

S. V. SAI BUILDERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
7Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
435 homeson the public record across 7 projects
48,429 sq mbuilt-up filed
28,623 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
NAGARAM
Village
Nagaram
Mandal
Keesara
District
Medchal-Malkajgiri
Pincode
500083
North boundary
CHARYS ARCADE AND 30 FEET WIDE ROAD
East boundary
PLOTTED AREA IN SURVEY NO 294
South boundary
ROAD AND PLOTTED AREA
West boundary
ROAD AND NEIGHBOURS PROPERTY
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 519m away
LifestyleNo parks within 2km · Gym or sports centre 1.6km away
ShoppingSupermarket 1.2km away · Mall 1.5km away · Bank 766m away
Getting around
Primary road 525 m · Chakripuram RoadRailway line 2.5 kmRailway station 2.5km away (Charlapalli)Bus stop within 1km
Water & environment
Water body 991 m
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Dry land, Land abutting NH/SH/ZPP/MPP, Agricultural Land fit for H.S.. The state classes land per survey— confirm your plot’s survey number is House Sites.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹3,000/sq ydHouse Sites

₹3,588/sq m · effective Jan 2013

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 293 PART

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.