HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
15
Buildings
2
Parking
119 spaces
Land area
1,550 sq m
Sanctioned built-up
7,458 sq m

Timeline

RERA registeredNov 2024
Proposed completionJun 2028
TodayJul 2026
Construction progress
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Stairs & lifts2%
Excavation100%
Basement (if any)100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SADGURU BUILDERS & DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
75 homeson the public record across 3 projects
11,979 sq mbuilt-up filed
3,811 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
City and Industrial Development Corporation (CIDCO)Development Authoritythis project1 of 2 projects
Town Planning Palghar1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ulawe
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
F-42 Sector 8
North boundary
6 m wide Road
East boundary
Plot No 39
South boundary
Plot No 30 and 31
West boundary
15 m wide Road
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.3km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 km · Ulwe FlyoverPrimary road 2.3 km · Panvel Uran RoadRailway line 201 m · Uran LineNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 209 m · CIDCO PondCanal 598 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. F-42 Sector 8
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.