Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
8
Parking
139 spaces
Land area
3,620 sq m
Sanctioned built-up
8,119 sq m
Recreational open space
362 sq m

Timeline

RERA registeredOct 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Sai Construction

PartnershipPromoter type
Thane, MAHARASHTRABased in
20Projects
14Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
902 homeson the public record across 20 projects
45,226 sq mbuilt-up filed
21,673 sq mland declared
₹59.33 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation3 of 15 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 15 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 15 projects
District Collector Of ThaneCollector officethis project1 of 15 projects
Indapur Municipal CouncilMunicipal Council1 of 15 projects
Kalyangarh MunicipalityMunicipality1 of 15 projects
Kulgaon Badlapur Municipal CouncilMunicipal Council1 of 15 projects
Nashik Municipal CorporationMunicipal Corporation1 of 15 projects
Others1 of 15 projects
Panihati MunicipalityMunicipality1 of 15 projects
Rajkot Urban Development AuthorityUrban Development Authority1 of 15 projects
Surat Municipal CorporationMunicipal / Corporation1 of 15 projects
Ulhasnagar Municipal CorporationMunicipal Corporation1 of 15 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Washind (CT)
Taluka
Shahapur
District
Thane
Pincode
421601
Survey no.
Survey No. 188/2/2
North boundary
12.00 M.W. Service Road
East boundary
5.00 M.W. Existing Road
South boundary
ADJ S.No. 189 A
West boundary
ADJ S.No. 192
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 462m away · 3 clinics within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 115 m · Mumbai Agra National HighwayPrimary road 1.1 km · Dugadphata roadRailway line 765 mRailway station 816m away (Vasind)Limited bus connectivity nearby
Water & environment
Water body 1.2 kmCanal 1.2 km · Bhatsa Right Bank Canal
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

District Collector Of Thane

Collector office
Building Permit
Survey no. Survey No. 188/2/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.