HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
130 plots
Land area
15,207 sq m
Recreational open space
3,260 sq m

Timeline

RERA registeredMay 2024
Proposed completionMar 2026
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

MAHESH SHANKARRAO GULHANE

IndividualPromoter type
Wardha, MAHARASHTRABased in
11Projects
3Cities
2020–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,102 plotson the public record across 11 projects
1,42,670 sq mplotted area
1,42,670 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Office Of District Collector, NagpurCollector officethis project1 of 2 projects
Sub Divisional Office Wardha1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Narsala (ri)
Taluka
Umred
District
Nagpur
Pincode
441203
Survey no.
Survey no 39
North boundary
Road
East boundary
F S No 40
South boundary
F S No 42
West boundary
F S No 38
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.1 km · Umred BypassPrimary road 931 mRailway line 2.8 kmRailway station 3.2km away (Umred)Limited bus connectivity nearby
Water & environment
Canal 1.7 kmWater body 1.8 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Office Of District Collector, Nagpur

Collector office
Layout Permit
Survey no. Survey no 39

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.