HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
49 units
Mix
39 × 1 BHK · 10 × 2 BHK
Carpet area
30–44 sq mper-unit range, as filed
Floors
12
Land area
991 sq m
Sanctioned built-up
4,742 sq m
Recreational open space
481 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2026
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

49 units across 4 batches
TypeArea sq mCount
1 BHK3110
1 BHK3019
2 BHK4410
1 BHK3210

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

SHREE SAMARTHA DEVELOPERS

PartnershipPromoter type
Palghar, MAHARASHTRABased in
3Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
49 homeson the public record across 3 projects
8,133 sq mbuilt-up filed
3,571 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Executive Engineer Nashik Munciple Corporation1 of 2 projects
Pune Municipal Corportaion1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
BHAYANDAR
Taluka
Thane
District
Thane
Pincode
401101
Survey no.
S NO 221 , NEW S NO 5 , H NO 1
North boundary
S NO 230
East boundary
D P ROAD
South boundary
S NO 231
West boundary
EXISTING ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.6km away
LifestyleNo parks within 2km
ShoppingSupermarket 1.3km away
Getting around
Primary road 3.7 kmRailway line 3.2 kmMetro station 2.1km away (Subhash Chandra Bose Ground)Limited bus connectivity nearby
Water & environment
Water body 177 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.