Timeline

RERA registeredJan 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal finishes50%
Stairs & lifts50%
Superstructure90%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAI CITY PROMOTERS AND DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kopargaon (R)
Taluka
Kopargaon
District
Ahmednagar
Pincode
423601
Survey no.
206/3/3 plot no 3
North boundary
9 mtr road
East boundary
Plot no 4 5 6
South boundary
12 mtr road
West boundary
24Mtr D P road
What’s nearby
Schools1 school within 500m · College or university 928m away
HealthcareHospital 322m away
LifestylePark 2.0km away
ShoppingNo supermarket within 2km · Bank 451m away
Getting around
Expressway 1.2 kmRailway line 3.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 697 mWater body 3.6 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kopargaon Municipal Council

Municipal Council
Building Permit
Survey no. 206/3/3 plot no 3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kopargaon Municipal Council

Municipal corporation

Has approved 10 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
9
On record
0 flats · 0 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.