HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
24 spaces
Land area
1,546 sq m
Sanctioned built-up
1,838 sq m

Timeline

RERA registeredAug 2017
Proposed completionJan 2019
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

sai samrajya developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wadagaon (CT)
Taluka
Mawal
District
Pune
Pincode
412106
Survey no.
53,54/4,55/2,56/3,54/2, Plot no-69,72,73
North boundary
ROAD
East boundary
SURVEY NO 54
South boundary
ROAD
West boundary
ROAD
What’s nearby
SchoolsNo schools within 2km · 3 educational institutions within 1km · Library 369m away
HealthcareHospital 153m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 591m away · 8 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Convenience store within 1km · Bank 9m away
Getting around
Primary road 588 m · Pipeline RoadRailway line 43 mRailway station 223m away (Badlapur)3 bus stops within 500m
Water & environment
Water body 102 m · Mahalaxmi Lake
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. 53,54/4,55/2,56/3,54/2, Plot no-69,72,73

The promised possession date (31 Jan 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.