Complete project overview

MahaRERA · Registration filing
Floors
11
Buildings
36
Parking
193 spaces
Land area
7,816 sq m
Sanctioned built-up
18,400 sq m
Recreational open space
3,184 sq m

Timeline

RERA registeredNov 2022
Proposed completionOct 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
OC-readiness0%
Water conservation…0%
Water Supply25%
Flat fit-out40%
Stairs & lifts50%
Internal Roads & F…50%
Sewerage (Chamber,…50%
External finishes80%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAKSHI CONSTRUCTION ANIL LAXMAN SAWANT

IndividualPromoter type
Satara, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Songirwadi (Rural) (CT)
Taluka
Wai
District
Satara
Pincode
412803
Survey no.
S NO 68, PLOT NO 1+2+3+OPEN SPACE
North boundary
ADJ CANNAL
East boundary
ADJ S NO 67
South boundary
PROPOSED WAI BAVDHAN ROAD 24M WIDE
West boundary
PROPOSED WAI BAVDHAN ROAD 24M WIDE AND SN 70-1
What’s nearby
Schools1 school within 500m
HealthcareHospital 279m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 726m away
Getting around
Primary road 236 mNo metro or railway within 5kmBus stop within 1km
Water & environment
River 362 m · KrishnaCanal 755 mWater body 880 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Planning Town Satara

Building Permit
Survey no. S NO 68, PLOT NO 1+2+3+OPEN SPACE
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.