HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
111 spaces
Land area
1,931 sq m
Sanctioned built-up
5,140 sq m

Timeline

RERA registeredAug 2025
Proposed completionAug 2030
TodayJul 2026
Construction progress
Basement (if any)0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Sewerage (Chamber,…0%
Plinth75%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

JJRV INFRA PRIVATE LIMITED

CompanyPromoter type
Solapur, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Solapur (M Corp.)
Taluka
Solapur North
District
Solapur
Pincode
413004
Survey no.
S.NO.27/6/1/2/3/B
North boundary
ROAD
East boundary
RTO
South boundary
MAHESH COACHING CLASSES
West boundary
NEW CONSTRUCTED BUILDING
What’s nearby
SchoolsNearest school 1.8km away
HealthcareHospital 564m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.4 km · Degaon RoadPrimary road 649 m · Vijapur RoadRailway line 1.1 kmRailway station 1.9km away (Solapur)Bus stop within 500m
Water & environment
Water body 1.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Solapur Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S.NO.27/6/1/2/3/B
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Solapur Municipal Corporation

Municipal corporation

Has approved 66 RERA projects0.3% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
60
On record
617 flats · 102 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.