MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
66 spaces
Land area
1,475 sq m
Sanctioned built-up
1,912 sq m

Timeline

RERA registeredNov 2023
Proposed completionMar 2028
TodayJul 2026
Construction progress
Podiums0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Energy managemcnt20%
Stilt floor90%
OC-readiness90%
Stairs & lifts95%
External finishes95%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Water Supply100%
Sewerage (Chamber,…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAI PRASAD BUILDERS & DEVELOPERS

PartnershipPromoter type
Ratnagiri, MAHARASHTRABased in
2Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
5,537 sq mbuilt-up filed
4,575 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Shringartali
Taluka
Guhagar
District
Ratnagiri
Pincode
415724
Survey no.
S. NO. 26/A/1/5
North boundary
ROAD
East boundary
HISSA NO 6
South boundary
HISSA NO 14 AND 15
West boundary
HISSA NO 4
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 71 m · Chiplun Guhagar RoadPrimary road 5.0 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.2 kmWater body 4.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Sub Divisional Officer Chiplun

Building Permit
Survey no. S. NO. 26/A/1/5
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Sub Divisional Officer Chiplun

Planning authority

Has approved 8 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
7
On record
0 flats · 0 plots
Since
2020

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.