Complete project overview

MahaRERA · Registration filing
Floors
8
Parking
4 spaces
Land area
1,559 sq m
Sanctioned built-up
2,183 sq m

Timeline

RERA registeredDec 2018
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Fire protection an…50%
Sewerage (Chamber,…60%
Electrical meter r…60%
Storm Water Drains65%
Water conservation…70%
Open Parking70%
Water Supply80%
Landscaping & Tree…80%
Flat fit-out90%
External finishes90%
OC-readiness90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RUGVED CONSTRUCTION CO

PartnershipPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2018–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Solapur (M Corp.)
Taluka
Solapur North
District
Solapur
Pincode
413007
Survey no.
27 2 D E
North boundary
PLOT NO 4
East boundary
60 FEET ROAD
South boundary
50 FEET ROAD
West boundary
PLOT NO 36-37 AND OPEN SPACE
What’s nearby
Schools1 school within 1km · College or university 1.6km away
HealthcareHospital 867m away
LifestylePark 1.3km away
ShoppingSupermarket 1.4km away
Getting around
Expressway 3.6 km · Degaon RoadPrimary road 180 m · Vijapur RoadRailway line 1.7 kmRailway station 3.1km away (Solapur)Bus stop within 1km
Water & environment
Water body 1.8 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.