HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
4
Parking
494 spaces
Land area
5,717 sq m
Sanctioned built-up
19,511 sq m
Recreational open space
572 sq m

Timeline

RERA registeredDec 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
External finishes0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Stairs & lifts2%
Basement (if any)60%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Today Realty

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kamothe
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Plot No.-11B, Sector – 22
North boundary
Plot No. 11A
East boundary
National Highway - 54B
South boundary
20 M Wide Road
West boundary
Plot No. 15
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 466m away · 1 clinic within 1km
LifestylePark 986m away · Gym or sports centre 1.2km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 688m away
Getting around
Expressway 61 m · Uran RoadPrimary road 891 mRailway line 740 mRailway station 1.1km away (Khandeshwar)Bus stop within 500m
Water & environment
Water body 335 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Panvel Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Plot No.-11B, Sector – 22
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Panvel Municipal Corporation

Municipal corporation

Has approved 305 RERA projects1.5% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
238
On record
4,602 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.