Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
85 spaces
Land area
898 sq m
Sanctioned built-up
2,002 sq m

Timeline

RERA registeredDec 2024
Proposed completionMar 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Open Parking0%
Stairs & lifts30%
External finishes30%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAVA DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Asangaon (CT)
Taluka
Shahapur
District
Thane
Pincode
421601
Survey no.
108/1/B/2
North boundary
ADJ S No 107
East boundary
ADJ S No 108
South boundary
Existing Road
West boundary
Plot No 1
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.8km away · 1 clinic within 1km
LifestyleNo parks within 2km · 6 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Expressway 639 m · Mumbai Agra National HighwayPrimary road 4.7 kmRailway line 156 mRailway station 113m away (Asangaon)Bus stop within 1km
Water & environment
Canal 876 m · Bhatsa Right Bank CanalWater body 879 mRiver 1.0 km · Bhairangi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector Office Thane

Collector office
Building Permit
Survey no. 108/1/B/2

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Collector Office Thane

Planning authority

Has approved 16 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
14
On record
0 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.