Complete project overview

MahaRERA · Registration filing
Floors
24
Buildings
2
Parking
60 spaces
Land area
1,447 sq m
Sanctioned built-up
1,434 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2024
TodayJul 2026
Construction progress
Podiums0%
Water conservation…0%
Fire protection an…75%
Flat fit-out80%
OC-readiness80%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SETHIA INFRASTRUCTURE PVT LTD

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
15,734 sq mbuilt-up filed
12,448 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 2 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Andheri
Taluka
Andheri
District
Mumbai Suburban
Pincode
400097
Survey no.
524 ,524 /1 TO 14 OF VILLAGE KURAR AND 358 ,358 /1 TO 11 OF VILLAGE MALAD EAST
North boundary
18 30 Road Line
East boundary
522 Village Kurar
South boundary
CTS 526
West boundary
359 Village Malad and 525 Village Kurar
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km · College or university 1.3km away
HealthcareHospital 548m away · 15 clinics within 1km · Pharmacy within 1km
Lifestyle1 park within 500m · 16+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 1.4km away · Convenience store within 1km
Getting around
Expressway 308 m · Western Express HighwayPrimary road 680 m · Swami Vivekanand RoadRailway line 608 mMetro station 482m away (Mogra)Bus stop within 1km
Water & environment
Water body 1.7 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 524 ,524 /1 TO 14 OF VILLAGE KURAR AND 358 ,358 /1 TO 11 OF VILLAGE MALAD EAST

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2013
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

4 complaints on MahaRERA’s register for this project 4 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.