Status
New Project Launch
Units
84 units
Unit mix
13 × FLAT · 13 × FLAT · 13 × FLAT · 13 × FLAT · 13 × FLAT · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP · 1 × SHOP
Towers
1
Floors
14
Land area
1,173 sq m
Built-up area
7,313 sq m
FAR sanctioned
4.62
Covered area
331 sq m
Open area
842 sq m
Land parcels
1 survey no

Timeline

Project startedJul 2024
RERA registeredSep 2024
Proposed completionJun 2031
TodayJul 2026
Construction progress

40% overall, as filed

Finishing0%
Internal infra0%
External infra0%
Amenities0%
Super-structure10%
Common areas16%
Sub-structure97%
From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

84 units across 24 batches
TypeArea sq mCount
FLAT5913
SHOP171
SHOP131
SHOP91
SHOP161
SHOP381
SHOP191
FLAT5413
SHOP141
SHOP141
SHOP141
SHOP121
SHOP1651
SHOP271
FLAT5713
SHOP131
FLAT3413
SHOP71
FLAT5713
SHOP181
SHOP121
SHOP161
SHOP491
SHOP101

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Karnataka · Promoter registration

Nidhi Land Infrastructure Developers India (P) Ltd.,

CompanyPromoter type
Dakshina KannadaBased in
3Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
156 homeson the public record across 3 projects
17,983 sq mbuilt-up filed
4,409 sq mland declared
₹54.25 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Mangalore
District
Dakshina Kannada
Pincode
575016
Address
SURVEY NO. 270/1 (P6), PADAV VILLAGE, , Mangalore , Mangalore , Dakshina Kannada, Karnataka - 575016
North boundary
Road
East boundary
Road
South boundary
Portion of Same Survey No.
West boundary
Portion of Same Survey No.
What’s nearby
SchoolsNearest school 1.4km away · College or university 1.7km away
HealthcareHospital 2.0km away
LifestyleNo parks within 2km · Gym or sports centre 1.8km away
ShoppingSupermarket 2.0km away · Bank 257m away
Getting around
Expressway 1.6 km · Solapur-Mangalore HighwayPrimary road 1.4 kmRailway line 1.2 kmRailway station 3.4km away (Padil)Limited bus connectivity nearby
Water & environment
Water body 1.8 km
distances only — not a flood assessment
Land, title & encumbrance
LandOwned + joint development (JDA)
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹18.76 Cr declared to build 84 flats. What that works out to:

₹22.33 Lakhdeclared cost per flatall-in — land + construction
₹2,383/sq ftof built-up area₹25,653/sq m
9%of the cost is land₹1,394/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Mangaluru Urban Development Authority

Urban Development Authority
approved 27 May 2024 · 2 yrs ago
Building Permit no. H7/BA 46/2023-24 (172652) KNPA 736/2023-24Survey no. 270/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan H7/BA 46/2023-24 (172652) KNPA 736/2023-24 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Mangaluru Urban Development Authority

Urban Development Authority

Has approved 440 RERA projectsabout 1 in 20 in Karnataka.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
315
On record
8,036 flats · 698 plots
Reach
6 taluks
Since
2017

More apartment-heavy than Karnataka overall — 96% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.