Complete project overview

MahaRERA · Registration filing
Units
58 units
Mix
21 × 2 BHK · 14 × 1 BHK · 10 × Room · 9 × Shop · 1 × Office · 1 × Reception · 1 × Resturant · 1 × Mangal Karyalay Dinn
Carpet area
14–620 sq mper-unit range, as filed
Floors
8
Buildings
2
Parking
94 spaces
Land area
1,142 sq m
Sanctioned built-up
4,042 sq m

Timeline

RERA registeredMar 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
External finishes0%
Water Supply0%
Sewerage (Chamber,…0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Stairs & lifts5%
OC-readiness10%
Superstructure13%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

58 units across 20 batches
TypeArea sq mCount
1 BHK347
2 BHK427
1 BHK307
2 BHK507
2 BHK457
Shop141
Shop141
Shop161
Office201
Room241
Room158
Reception291
Room281
Shop621
Shop571
Shop622
Shop601
Shop251
Resturant3201
Mangal Karyalay Dinn6201

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Laxmi Kamal Associates

PartnershipPromoter type
Thane, MAHARASHTRABased in
6Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
758 homeson the public record across 6 projects
34,975 sq mbuilt-up filed
26,026 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khuntavali
Taluka
Ambarnath
District
Thane
Pincode
421505
Survey no.
Plot no.B, S.no.5,H.no.24,CTS no.31/15, S.no.2,H.no.2,CTS no.55/1, S.no.2,H.no.3,CTS no.55/2
North boundary
Shankar Heights Phase 1
East boundary
24 Meter DP Road
South boundary
Orchid Woods
West boundary
CTS no 55
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 397m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.0 km · Kalyan-Nagar RoadPrimary road 673 m · Kalyan Badlapur RoadRailway line 1.2 kmRailway station 1.5km away (Ambarnath)Limited bus connectivity nearby
Water & environment
Water body 861 m
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.