HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
Completed
Towers
1
Land area
971 sq m
FAR sanctioned
1.54
Covered area
480 sq m
Open area
491 sq m

Timeline

Project startedFeb 2021
RERA registeredMar 2021
Proposed completionFeb 2023
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

GANESH M P

Dakshina KannadaBased in
6Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
95 homeson the public record across 6 projects
15,706 sq mbuilt-up filed
12,017 sq mland declared
₹64.50 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Mangalore
District
Dakshina Kannada
Pincode
575004
Address
SURVEY NO. 52/3(P) KADRI VILLAGE, MANGALORE CITY CORPORATION LIMIT , MANGALORE
What’s nearby
Schools1 school within 1km · College or university 1.0km away · Library 1.7km away
HealthcareHospital 549m away · 3 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.5km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Convenience store within 1km · Bank 619m away
Getting around
Expressway 575 m · George Fernandes RoadPrimary road 383 m · George Fernandes RoadRailway line 2.5 kmRailway station 2.7km away (Mangaluru Central)Bus stop within 1km
Water & environment
Water body 526 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹4.48 Cr declared. What that works out to:

10%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Mangaluru Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (12 Feb 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mangaluru Urban Development Authority

Urban Development Authority

Has approved 440 RERA projectsabout 1 in 20 in Karnataka.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
315
On record
8,036 flats · 698 plots
Reach
6 taluks
Since
2017

More apartment-heavy than Karnataka overall — 96% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.