Complete project overview

MahaRERA · Registration filing
Floors
2
Buildings
2
Parking
7 spaces
Land area
1,370 sq m
Sanctioned built-up
1,321 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
External finishes0%
Water Supply0%
Storm Water Drains0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
OC-readiness5%
Internal finishes10%
Stairs & lifts25%
Superstructure50%
Sewerage (Chamber,…50%
Stilt floor90%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

GURU OM CONSTRUCTION AND DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
421204
Survey no.
155 PART 10
North boundary
S NO 155 PART 11
East boundary
S NO 162
South boundary
S NO 155 PART 9
West boundary
EXISTING ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away
LifestylePark 1.7km away · Gym or sports centre 1.7km away
ShoppingNo supermarket within 2km
Getting around
Expressway 2.2 km · ShilphataPrimary road 143 m · Kalyan - Shil RoadRailway line 1.7 kmRailway station 1.8km away (Nilaje)4 bus stops within 500m
Water & environment
Water body 139 m · Khidkali LakeRiver 1.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 155 PART 10

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.