Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Land area
477 sq m
Covered area
283 sq m
Open area
194 sq m

Timeline

Project startedOct 2020
Proposed completionDec 2022
RERA registeredJul 2023
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

ADWAII CONSTRUCTION

BelagaviBased in
2Projects
1City
2020–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
863 sq mland declared
₹6.43 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Belagavi
District
Belagavi
Pincode
590006
Address
CTS 1360/6, 1ST CROSS, VIDYAGIRI AZAMNAGAR
What’s nearby
Schools1 school within 500m · 12 educational institutions within 1km · College or university 329m away
HealthcareHospital 372m away · 4 clinics within 1km
LifestylePark 879m away · Swimming pool within 2km
ShoppingSupermarket 1.3km away · Mall 936m away · Bank 501m away
Getting around
Expressway 1.7 km · Congress RoadPrimary road 1.1 km · Atal Bihari Vajpayee MargRailway line 1.7 kmRailway station 2.1km away (Belagavi)Limited bus connectivity nearby
Water & environment
Water body 1.1 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹3.31 Cr declared. What that works out to:

45%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Belagavi Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Belagavi Urban Development Authority

Urban Development Authority

Has approved 116 RERA projects1.3% of Karnataka.

an apartments market82% apartments · 18% plotted layouts. Apartments like yours are this body's core business.

Builders
98
On record
3,214 flats · 392 plots
Reach
8 taluks
Since
2017

More apartment-heavy than Karnataka overall — 82% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.