HORIZON
Share

SHIVTIRTH

P51700078666 · MahaRERA · https://gethorizon.in/projects/shivtirth-ambarnath-m-cl-thkayk0d

01

Complete project overview

MahaRERA · Registration filing
Units
24 units
Floors
8
Buildings
2
Parking
33 spaces
Land area
467 sq m
Sanctioned built-up
1,253 sq m

Timeline

RERA registeredJan 2025
Proposed completionDec 2027
TodaySep 2026
Construction progress
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Internal finishes75%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MANGALYA REALITY

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ambarnath(M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421501
Survey no.
CTS NO 8855A
North boundary
9 MTRS MUNICIPAL ROAD
East boundary
PLOT BEARING CTS NO 8851
South boundary
PLOT BEARING CTS NO 8801
West boundary
PLOT BEARING CTS NO 8856
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 88m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.4 km · Ahilyanagar - Kalyan Road | Bhiwandi - Murbad Road | B K Birla RoadPrimary road 587 m · Kalyan Badlapur RoadRailway line 224 mRailway station 296m away (Ambarnath)Limited bus connectivity nearby
Water & environment
River 1.1 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹47,492per sq yd
₹56,800per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Ambarnath(M Cl)”.
In force
2026-2027 schedule
Spread
₹40,970₹47,994 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Ambernath Municipal Council

Municipal Council
Building Permit
Survey no. CTS NO 8855A
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Ambernath Municipal Council

Municipal corporation

Has approved 114 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
99
On record
970 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,683 residential projects still under way within 25 km. Step out ring by ring:

64 projects within 1 km — showing the nearest 6.

KhuntavaliResidential / Group Housing

PARAS APARTMENT CO-OP. HOUSING SOCIETY LTD

SHIV INFRA

Oct 2024registered
Jun 2027target completion
Government Guidance Rate₹24,164/sq ydScale55 flatsAuthorityMahaRERA
KhuntavaliResidential / Group Housing

SKY HERITAGE

Faisal Constructions

Apr 2025registered
Dec 2027target completion
Government Guidance Rate₹24,164/sq ydScale87 flatsAuthorityMahaRERA
AmbarnathMixed

SUMANT CHS LTD

GPS LIFESPACE

Mar 2026registered
Oct 2028target completion
Government Guidance Rate₹47,492/sq ydScale33 flatsAuthorityMahaRERA
AmbarnathResidential / Group Housing

AAI NIWAS

AAI MAULI ENTERPRISES

Dec 2025registered
Mar 2027target completion
Government Guidance Rate₹47,492/sq ydScale22 flatsAuthorityMahaRERA
AmbarnathOthers

Neelkrishna amalgamated project of Neelam CHS Ltd and Krishna Milan CHS Ltd

OM SAI INFRA

Feb 2023registered
Mar 2027target completion
Government Guidance Rate₹47,492/sq ydScale117 flatsAuthorityMahaRERA
AmbarnathOthers

DATTA KUTIR

SPARSH BUILDCON

Jul 2023registered
May 2026target completion
Government Guidance Rate₹47,492/sq ydScale87 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.