Complete project overview

MahaRERA · Registration filing
Units
197 units
Mix
173 × 1 BHK · 23 × 2 BHK · 1 × 1 RK
Carpet area
16–56 sq mper-unit range, as filed
Floors
25
Buildings
5
Parking
93 spaces
Land area
3,850 sq m
Sanctioned built-up
5,739 sq m
Recreational open space
1,008 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2021
TodayJul 2026
Construction progress
Street Lighting0%
Aggregate area of …0%
Open Parking0%
Water conservation…50%
Landscaping & Tree…60%
Water Supply66%
Storm Water Drains66%
Fire protection an…66%
Internal Roads & F…75%
Sewerage (Chamber,…75%
Electrical meter r…80%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
OTHER SOCIETY OFFI…100%
OTHER FITNESS CENT…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

197 units across 14 batches
TypeArea sq mCount
1 BHK3422
1 BHK3519
1 BHK3723
2 BHK4521
2 BHK461
2 BHK561
1 BHK3022
1 BHK3423
1 BHK3522
1 BHK289
1 BHK309
1 RK161
1 BHK2512
1 BHK2612

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

ATHARVA DEVELOPERS

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
17Projects
7Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
551 homeson the public record across 17 projects
44,671 sq mbuilt-up filed
13,489 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
17451 of 3 projects
Maharashtra Housing and Area Development Authority (MHADA)Housing Authority1 of 3 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authoritythis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400042
Survey no.
1050 1051 PT 1052 1053 AND 1058
North boundary
CTS 1056E Aditya Society
East boundary
CTS 1060B Omkar Society
South boundary
CTS 1040 Keni Chawl
West boundary
CTS 1038 Hunde Niwas
What’s nearby
Schools2 schools within 1km · College or university 1.4km away · Library 1.6km away
HealthcareHospital 202m away · 1 clinic within 1km
LifestylePark 1.8km away
ShoppingSupermarket 795m away · Mall 1.4km away
Getting around
Expressway 737 m · Eastern Express HighwayPrimary road 721 m · Lal Bahadur Shastri MargRailway line 423 mRailway station 742m away (Kanjur Marg)Bus stop within 1km
Water & environment
Water body 1.6 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. 1050 1051 PT 1052 1053 AND 1058

The promised possession date (30 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2016
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.