HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
69
Buildings
2
Parking
48 spaces
Land area
646 sq m
Sanctioned built-up
2,826 sq m
Recreational open space
3,801 sq m

Timeline

RERA registeredJun 2022
Proposed completionDec 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

SHRADDHA LANDMARK PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
21Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
935 homeson the public record across 21 projects
94,426 sq mbuilt-up filed
57,736 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Slum Rehabilitation AuthoritySlum Rehabilitation Authority7 of 13 projects
Maharashtra Housing and Area Development Authority (MHADA)Housing Authority3 of 13 projects
Maharashtra Housing & Area Development AuthorityDevelopment Authoritythis project2 of 13 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400083
Survey no.
356 PT
North boundary
Building No 5
East boundary
Internal DP Road
South boundary
Building No 3
West boundary
Eastern Express Highway
What’s nearby
SchoolsNo schools within 2km · College or university 1.8km away
HealthcareHospital 1.9km away · 3 clinics within 1km
LifestylePark 580m away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.9 kmPrimary road 1.7 km · Jogeshwari Vikhroli Link RoadRailway line 2.5 kmMetro station 2.0km away (Goregaon (East))Limited bus connectivity nearby
Water & environment
Water body 927 m · Chota Kashmir Lake
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing & Area Development Authority

Development Authority
Building Permit
Survey no. 356 PT

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Metropolitan / Development Authority

A regional planning body — a metropolitan region development authority (MMRDA/PMRDA), CIDCO, MHADA or the Slum Rehabilitation Authority. It has approved 2,760 RERA projects across 14 districts about 1 in 7 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.