HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
3
Parking
20 spaces
Land area
1,071 sq m
Sanctioned built-up
3,342 sq m

Timeline

RERA registeredApr 2024
Proposed completionMar 2028
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes40%
Stairs & lifts70%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ARJUN NITIN PATIL

IndividualPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431009
Survey no.
PLOT NO 33A,33B,34,35&36 GUT NO 46 /PART
North boundary
ROAD OF 25 FEET
East boundary
OPEN SPACE OF SOCIETY and Plot no 20 21 22
South boundary
ROAD OF 6 METER
West boundary
ROAD OF 18 METER
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 638m away · Clinic within 2km
Lifestyle1 park within 500m
ShoppingSupermarket 1.5km away
Getting around
Expressway 1.2 km · Beed Bypass HighwayPrimary road 1.5 kmRailway line 576 mRailway station 346m away (Mukundawadi)Limited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Others

Building Permit
Survey no. PLOT NO 33A,33B,34,35&36 GUT NO 46 /PART
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Others

Planning authority

Has approved 30 RERA projects0.1% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
27
On record
813 flats · 264 plots
Reach
11 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.