HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
8
Parking
213 spaces
Land area
3,550 sq m
Sanctioned built-up
7,924 sq m

Timeline

RERA registeredNov 2024
Proposed completionAug 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Electrical meter r…0%
Internal finishes35%
Stilt floor70%
Superstructure75%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAFAL DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
6Projects
4Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
473 plotson the public record across 6 projects
7,924 sq mbuilt-up filed
3,550 sq mland declared
₹62.32 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
IndoreTown & Country Planning (DTCP)5 of 6 projects
Penn City Councilthis project1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pen (M Cl)
Taluka
Pen
District
Raigarh
Pincode
402107
Survey no.
272A/2,272/A/3/2,272/A/3/3,272A/3/1 Part,283/A/3/3,283/A/3/2,283 A/2
North boundary
9 MTR WIDE ROAD AND SURVEY NO 265A
East boundary
9 MTR WIDE ROAD AND SURVEY NO 272-3-1PT
South boundary
SURVEY NO 272A-4-5-6
West boundary
SURVEY NO 270 272A AND272-6
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 683m away · 8 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 547m away
Getting around
Expressway 181 mRailway line 107 mRailway station 15m away (Pen)Limited bus connectivity nearby
Water & environment
Water body 661 mRiver 1.6 km · Bhogeshwari
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Penn City Council

Building Permit
Survey no. 272A/2,272/A/3/2,272/A/3/3,272A/3/1 Part,283/A/3/3,283/A/3/2,283 A/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.