This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
13
Buildings
4
Parking
14 spaces
Land area
4,309 sq m
Sanctioned built-up
10,759 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2019
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

ABHAY YASHWANT THITE

IndividualPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2017–2019Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401303
Survey no.
392/A PLOT NO-2 PLOT NO-4 MHADA COLANY BOLINJ VIRAR-401303
North boundary
LAYOUT PLOT NO 11-12-13
East boundary
12 METER WIDE ROAD
South boundary
9 METER WIDE ROAD
West boundary
12 METER WIDE ROAD
What’s nearby
SchoolsNearest school 1.7km away · College or university 1.9km away
HealthcareHospital 697m away · 2 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Swimming pool within 2km
ShoppingSupermarket 1.9km away · Convenience store within 1km
Getting around
Primary road 1.7 km · Manvel PadaRailway line 1.5 kmRailway station 1.9km away (Virar)Limited bus connectivity nearby
Water & environment
Water body 891 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 392/A PLOT NO-2 PLOT NO-4 MHADA COLANY BOLINJ VIRAR-401303

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Compliance1 non-compliance notice on record
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

3 complaints on MahaRERA’s register for this project 3 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.